Consulting Engineer

Curriculum Vitae  
Education & Training  
Forensic Cases  
Papers Presented  
Professional Activities  
Personal History  
Honors  

        

Copyright ©1998-2001
Design by CodeQwest


Electrical


Forensic


Fire Protection


Typical Forensic Engineering Cases
 

Medium Voltage (4,160 to 24,900 Volts)

Case 1 - A southern California  high school had suffered two cable failures in the same  manhole, each leading to an  electrical fire.  After the first fire, the general contractor had assumed that there was poor workmanship in the 4,160 volt electrical installation, and the electrical subcontractor was required to rewire the installation. After the second fire,  there was uncertainty about the cause.  The architect-engineer pointed to the utility and to the contractors.  The utility pointed to the workmanship.  Mr. Love was brought in months later to determine the basic cause.  This was actually easy because  the utility had furnished a grounded power source, and the architect-engineer had designed an ungrounded 4,160 V system.  Next was the task to learn why there was a failure and what were the exacerbating conditions which led to fires each time.  What developed was that the utility, the architect-engineer, and the electrical subcontractor all had some responsibility.  Following the resolution, the underground distribution system was completely rewired.

Case 2 - An unattended transit system converter station (convert AC voltage to DC) caught fire, and was almost completely destroyed.  Part of the problem was the type of grounding associated with the utility source.  As such, the converter station had inadequate protection for this service, and failed when the first surge developed.  Because this  happened during the startup phase, the failure detecting equipment had not been made  operational.  The initial failure and subsequent manifestation were undetected for  a long  period.  Identifying the cause required examination of documents between the engineer and the utility. The extent of the failure would have been mitigated if the remote alarm system had been operational.

Case 3 - A mylar balloon  touched overhead  power distribution conductors, causing arcing  and subsequent falling of bare conductors to ground,  resulting in injuries and vehicular damage.  The tavern operator  had distributed balloons during a basketball game being shown on the tavern TV.  Afterwards, one or more balloons were released, and at least one of them bridged the space between the three phase conductors of the 12,470 volts distribution system.  Mr. Love was brought in at the last minute, after the discovery period, and was deposed by an attorney for a plaintiff who had suffered physical and monetary damage. What Mr. Love discovered was that some utility controls had failed, and  that its protection scheme was inadequate.  Up to that point, the utility had not admitted any responsibility, but subsequently agreed to discuss a settlement.

Case 4 - An industrial facility had expanded its 12, 470 V distribution system, and purchased a new air circuit breaker for installation in a spare cubicle.  Prior to inserting the breaker, two workers entered the energized cubicle to verify the wiring and installed devices, and due to some accident, became exposed to an arc blast which caused considerable injury to each man.  Mr. Love was hired by the facility operator's attorney to investigate the damage and probable cause.  His efforts were those of a consultant, and subsequently the attorneys were able to assign the responsibility to a contractor whose personnel were involved..
 
Case 5 - An industrial facility hired an electrical contractor to perform extensive testing on the 24,900 V and 480 V systems during a holiday shutdown.  During the afternoon prior to the testing, the low voltage test crew arrived, and were shown the 24,900 V system by the plant engineer.  The doors to the metal-enclosed switchgear were left open, and two experienced electricians entered one cubicle without realizing that the switchgear was still energized.  The first electrician came too close to an energized component, and was electrocuted, with the accompanying arc knocking down and injuring the second electrician.  The attorney for the switchgear manufacturer hired Mr. Love as a consultant to advise on the safety conditions, warning signs, interlocks, and industrial practices relating to top vs bottom entry.

Case 6 - A generator protective relay  repeatedly tripped a generator circuit breaker when the co-generating unit was being paralleled to a utility.  After checking calculations and relay settings, Mr. Love determined that the problem lay in the current transformers which supplied current to the protective relays. Disassembly of switchgear revealed  that the current transformers had incorrect ratios and had to be replaced.

Case 7 - Involved a field of over 60 wind turbine generators. An electrical surge developed on the collection grid into which these generators fed power. During this incident, the surge protection furnished by the manufacturer failed on each of the sixty 480 V electrical panels, leading to many electrical panel fires. No personnel were involved, but the manifestation of the arc was evident in each of the destroyed electrical panels. In each case, the air was ionized around the failed surge device, leading to the destruction of many electrical panels. My study was to determine how that surge was generated, whether the surge protection was adequate and located properly on the 60 electrical panels, and if other protection was adequate Low Voltage 120 to 480 Volts.

Case 8 A large metal processing plant was brought to a halt by an electrical failure, causing buildup in the process pressure vessels, which ruptured and sent parts flying almost a half-mile away. My task was to determine whether recently added digital protective relays malfunctioned, leading to the failure of the 13.8kV ring bus. The plant had five 13.8 kV generators connected to a ring bus system, with an additional supply from the utility. In the event of an electrical fault, the new digital relays were to identify the location of the fault, then to initiate isolation of the faulty bus section by selectively opening the ring bus, yet permitting uninterrupted supply to the other loads.  

Case 9 - There was a residential fire  involving an attic furnace.  A suit  had been filed alleging that the capacitor in the fan motor circuit had failed, and  had ignited combustible building material.  Some experts had supported this theory, although no comparative cases could be cited.  Subsequently analysis of the circuit proved that this type of failure would have had to occur when the motor was running, but no smoke had been reported.  Thus the cause had to be from a different failure.

Case 10 - There was a fire in a museum elevator, with extensive damage in the elevator area, including the loss of some paintings and other art objects.  Investigating the burnt elevator proved that the fire could have developed from several scenarios.  One possible cause had been lighting fixtures, but an analysis of its failure mode showed that this scenario was quite remote.

Case 11 - A fire developed in a 480 V bus duct which carried power from the basement to the top floor of a 24 story  building.  At each floor, transformers reduced voltage to 120/240 V for distribution in office areas. The client had worked on the 120/240 V side of the transformers, and we proved that his work could not have caused the failure in the 480 V bus duct distribution system.

Case 12 - Heavy rains leaked through the roof of a manufacturing plant, penetrating into a 480 V bus duct (busway), tripping off the supply breaker, and shutting down the plant. An electrical contractor sent in his crew to dry out the system, and restore it to working order.  After the drying operation was deemed to be successful,  the main circuit breaker was closed, and then all branch circuit breakers were closed. Circuit breakers were plugged into the bus duct one at a time, until one circuit breaker bus plug could not be fitted securely.  The lead contract electrician allegedly hammered the plug, but instead of fitting the breaker in place, an arc developed which blew the man off the ladder, causing him to suffer arc burns. From the technical point of view, it was necessary to demonstrate that the purpose of a 480 V Ground Fault Protection system was to protect equipment and not personnel, and that Ground Fault Circuit Interrupters (GFCI) were not applicable.

Case 13- Two maintenance workers had the responsibility to keep a mall air conditioning system working. Neither was trained in air conditioning nor in electrical maintenance, but did whatever had to be done in a rarely supervised role. A 480 V three phase circuit breaker supplied power to a large air conditioning unit. Because that breaker ran in a hot condition, the workers had scheduled its replacement. They arrived at the mall at an early morning hour, and removed the circuit breaker panel cover plate in order to made it easier for the electrician to replace the breaker later.

However, something happened during (or after) the removal step, and an explosion within the panel developed a fireball that passed closely by one man and struck the second in the chest. Both were horribly burned. An ambulance took one man to the hospital, where he survived with burns over most of his body. There was a delay before the second ambulance arrived and the second man expired on the way to the hospital. My participation was to advise a plaintiff's attorney on the scenario which had been developed by some observers and the surviving worker. The fire department did an excellent job in photographing the scene.   

Case 14 – A TV Cable contractor employee was assigned to work on a utility pole that supported power, telephone and TV cables.  The employee sensed a live voltage as he climbed upward.  After falling to the ground, he was transported to a nearby hospital and treated mainly for injuries suffered as a result of the 20-foot fall.  Technicians from the local power company measured this lethal voltage, and determined the source to be a ghost ground voltage caused by improper grounding in an adjacent facility. Mr. Love was hired by the local telephone company, and recognized that this condition was probable on the power company’s corner-grounded delta distribution system   Spacing and orientation were in accord with accepted standards for this type of installation.

Case 15 – A fire caused extensive damage to the interior of a shop used for tailoring of all types.  The immediate cause was verified by the fire department to be a damaged extension cord that ran from the panel to the rear of the shop.  The renter claimed that the panel circuit breaker should have protected the extension cord.  Mr. Love was hired by the property owner to explain in court how a circuit breaker worked and the unacceptability of using an extension cord in lieu of permanent wiring. 

Case 16 –An arc developed in the incoming 3000A circuit breaker cubicle of a large 480 Volt switchgear.  A ground fault relay detected this fault and tripped the supply breaker.  Mr. Love was hired to investigate this Washington DC government facility, and to determine the cause.  Numerous instances were evident where the bus tie bolts were not properly and adequately torqued.  Vibration over a long period led to loose bolts and subsequent arcs. Another consultant had recommended raising the setting, but because the accident happened when it did, the low setting on the ground fault relay saved the facility from very extensive damage. 

ARBITRATION

Case 17  - An independent generator of electricity had unexpected construction costs, including excessive overtime. The case went to arbitration as per agreement.  After studying the drawings and installation, was able to support management position that construction had drawings, material, and equipment on schedule, and the amount of overtime was not warranted.  Testimony was very influential per company attorney in writing.


There were many cases where Mr. Love supported the work of associates in determining code violations,  preparing  calculations to determine the magnitude and probability of certain failures, and furnishing data from his extensive library of technical material.


      

Copyright ©1998-2001
Design by CodeQwest
Curriculum Vitae Education & Training Forensic Cases
Professional Activities Personal History Honors